Hello Pavan,
In case of Minimizing KPI type, the critical value should be more than a warning. According to your example, the critical value should have been more than 50% of Budget. In that case, see the expected color in different scenarios is shown below:
1. When Budget is 10000 and Actuals is 2000 The Bar color should show Green color --> correct bar color should be in green color
2. When Actuals is 3000 (i.e., greater than Critical value) The Bar color should show Amber colour --> incorrect because critical value should be more than a warning, so the bar color should be still green.
3. And When Actuals is 6000 (i.e., greater than Warning value) The Bar color should show Red Colour. --> should be in red color when the critical value is more than 50% of the budget.
For further assistance in Smart Business Service, you can create an Incident on SAP Support Portal with the components: CA-GTF-SB-HCP. You may also contact Smart Business team at smartbusiness@sap.com