Hi,

The scenario is service industry ex. House keeping service.

We are using Project system module for the above service industry. The modules which are being implemented apart from PS are SD, MM, FICO and HR.

The Project duration is normally 1 year. The client requirements are as follows:

1) Quotation price should be based on the planned cost of the project (No Inquiry)

2) Create a Contract once Quotation is approved.

3) Month wise billing based on actuals of resource and materials consumed for the project.

As per my understanding, Resource related billing and Easy cost planning to be used. Pl let me know whether this is correct and let me also know how to handle the above scenario.

Rgds,

Prasad

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Prasad,

We are building at this moment the scenario's you are describing. We use assembly processing for automatically creating project structures triggered by a sales order item. We don't use easy cost planning and plan the cost directly on the network activities. We have build scenario's for time and material (using RRB and DIP) and fixed price (having specific pricing schemes in place).

Regards,

Paul