hi Sir

At time of Usage Decision RMC concrete Material Usage Decision 28days Results are Awaited i give UD Accepted under deviation but after 28days how to add 28days Concrete RMC Results valve in QM SAp. means Results Revise.

Please suggest ASAP.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Arijit Banerjee Jul 17, 2017 at 04:51 PM
0

For the RMC Concrete material, use MIC's which are 'Long Term Inspection' active. Then even after you have used Accepted UD code "A" or "A1", after 28 days, you can still visit the same inspection lot in QA12 and update those LT MIC inspection results. There are multiple discussion available in SCN on this subject, please can you explore this a bot more. Thanks.

Share
10 |10000 characters needed characters left characters exceeded
Arijit Banerjee Jul 17, 2017 at 04:52 PM
0

You need not use Reversing UD as that's not a best practice to be followed in QM.