Hi,

i have a maintenance plant 0001 which is also a maintenance planning plant. There is another plant 0002 where the materials are stored central.

When I'm creating a Task list it is not possible to add components from plant 0002, because it says they don't exist at plant 0001.

Is there a way to add components (which are from plant 0002) to a Task list (for plant 0001)?

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Jul 19, 2017 at 07:27 AM

    Dear S B,

    You need to extend the material from Plant 0002 to Plant 0001.

    Regards,

    PS R

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 19, 2017 at 07:06 AM
    Add comment
    10|10000 characters needed characters exceeded

  • Jul 19, 2017 at 01:56 PM

    When I extend the material to Plant 0001 doesn't it means that the material is stored in Plant 0001?

    But the materials are stored in Plant 0002.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 28, 2017 at 02:07 PM

    Any Suggestion?