Hi,

i have a maintenance plant 0001 which is also a maintenance planning plant. There is another plant 0002 where the materials are stored central.

When I'm creating a Task list it is not possible to add components from plant 0002, because it says they don't exist at plant 0001.

Is there a way to add components (which are from plant 0002) to a Task list (for plant 0001)?

Regards

Accepted Solutions (0)

Answers (4)

Answers (4)

stefan_bogesch
Participant
0 Kudos

Any Suggestion?

peter_atkin
Active Contributor
0 Kudos

Did you read the link above?

You can use BOMs to resolve the issue.

PeteA

stefan_bogesch
Participant
0 Kudos

When I extend the material to Plant 0001 doesn't it means that the material is stored in Plant 0001?

But the materials are stored in Plant 0002.

Regards

psr2412
Contributor
0 Kudos

Dear S B,

You need to extend the material from Plant 0002 to Plant 0001.

Regards,

PS R