How to plan multiple product on one work center in SAP S/4 HANA

Hi,

Scheduling of multiple product on single work center is a challenge for me right now. please suggest if any solution

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 17, 2017 at 07:53 PM

    Hello

    Can you please describe your issue in more detail? Why is this a challenge for you?

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Mr. Caetano,

      I have checked the scenario using the individual capacities option of work center and spitting function.

      and while creating order changed the split number and planned multiple product at same time and on same work center.

      successfully tested the scenario.