Hi Experts,
Can you please advise what is the best way to charge overtime, either to create a activity type with a different rate , or via CATS, are there any multiplier functionality is in the system in Activity type or in CATS.
Please advise.
Regards
Ashu.
Hi,
It is advisable to use CATS. As in CATS, the timesheet are maintained. Based on the timesheet and activity attached, the cost are charged either to project or order.
Hope this helps, if yes, please assign points and close the thread.
Regards,
Harish