regarding requisitions

Former Member
0 Kudos

Hi All,

once we have created demand or planned orders for materials.....it have to rise a requisition to purchase those materilas...where do we can configure that auto rising of PR once we have creat demand for that material..

and where do we can see those created requisiti?

Can anyone pls help me with this?

Regards,

Murali.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You can see the PR No at Sales Order -> Item data -> Schedule Lines

Go for the Procurment tab OR

While creating the Purchase Order with respect to PR, for selecting thePR by drill down select option as Purchase Requisition Per Sales Document.Put sales order No.u get PR NO.

Reward if helpful..

Regards

sanjay L

Former Member
0 Kudos

If you set your MRP run -MD03/MD02 to create purchase reqs in the opening period then purchase reqs are created automatically after the MRP is run.

You can view this using the Stock requirements-MD04 or MRP list MD06

Former Member
0 Kudos

Hi Saritha,

Here in MD04 or MD06 we can see the planned orders only...but where can we see the automatically created requisitions...

More over how can the purchasing department will be notified about the requsitions rised....?

Regards,

Murali.

Former Member
0 Kudos

You have to run MRP first-MD02/MD03 and while doing that select the "create reqs" tab ( beneath the MRP processing key) . So instead of planned orders reqs are created.

The reqs can be viewd by purchasing using ME5A, ME56 etc.

Former Member
0 Kudos

Hi,

If you set the correct flags on the MRP run the system will generate the requisitions automatically (make sure that you use PD as the MRP type on the material master record).

As for how your Purchasing department get to know about these reqs, you should tell them that they have to check for any P reqs for their P group regularly and at the very least every day, using ME57/58 etc.

Steve B