on 06-28-2007 3:51 PM
hi all
can anyone plz tell me the standard workflow for pr release (item wise) and the task associated with it
regards
navjot
hi rose and davis
thank u both for ur replies
i have a senario that when a approver does not approve a requisition for 5 days it automatically gets to the next approver . how can this be achieved
what i have done is i have put the same workflow as subworkflow for he obsolete step witha aim to start the wokflow again with approver corresponding to next release code . how can i increment or get the next release code in this case.
if i am opting a wrong method do suggest an alternative.
regards
navjot
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Put deadline monitoring, based on the outcome after 5 days call another method (background) and release the requistion in background. This will trigger workflow for next release code. You can give some description in the task and mention over there that the req wqs released in background as there was no response.
Thanks,
Shweta
hai pls go through the following link http://help.sap.com/saphelp_erp2005vp/helpdata/en/1d/ea9d9c7aca11d194b70000e82dec10/frameset.htm
Item-Wise Release-------TS00007986
Workflow: 00000038
Overall Release----
TS20000159
Workflow: 20000077
regards
rose
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Navjot,
The Std wf for Pr release is WS00000038 and the task associated with it is TS00007986.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
10 | |
9 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.