Change in Control code of material master irrespective of plant

Jul 16, 2017 at 09:58 AM

97

avatar image

Dear all SAP expert,

Our company have 4 plant. Same material code maintained for all plant. Is that possible if we change control code of material for one plant than it will reflect to all other plant similar way whatever we change UOM of a material for one plant than it will reflect for all other plant? Please suggest the procedure.

Thanks in advance

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
Jul 16, 2017 at 03:57 PM
2

Units of measures defined in the material master alternative units tab are global and affect the entire material master, no matter how many plant it has.

Control code is a field in the material master export/import tab and kept at plant level, hence you have to change it individually for each plant.

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Thanks for your response.

But can we define Control code field globally?

Thanks in advance

0

NO you cannot