Hello Experts,

There are 8 storage location in Plant 0001. Storage location REJ1, Storage location REW1, Storage location SCR1. under plant 0001. Now client wants restrict from MRP Run these 3 storage location and system should not consider the stock availability at these 3 storage location while generating MRP out put.

Please suggest me.

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Jul 16, 2017 at 06:32 PM

    Hello

    Please observe that the value in MMSC is only a default vale for the creation of new materials. For materials already created, you should maintain this value directly in the material master tab MRP4.

    In addition, this solution does not work in S/4 HANA and you should use MRP areas in S/4 to map this scenario.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 17, 2017 at 06:50 AM

    Hello Caetano/ Rajashekara sir,

    Many thanks for your quick response.

    I had already tried this one. There are above 100 raw material these three storage location. If in case i assigned in MMSC in MRP - 1 then in future how can change it. This solution not accepting plant 0001 Users.

    Please suggest me any other options.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 16, 2017 at 04:30 PM

    Hi,

    Could you please try with the below option

    T code : MMSC
    Maintain the Indication for MRP : 1 : Storage location stock excluded from MRP ( Please take a look of the attached screen shot)

    Hope, this will be of useful info. Kindly check & let me know with your feedback

    Many Thanks for your quick feedback : Raja Sekhara Reddy B

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 20, 2017 at 11:04 AM

    Hello ,

    Please have a look onto this thread . it will help you

    https://archive.sap.com/discussions/thread/3211154

    In configuration setting and in following path you have option to exclude the storage location from the MRP for the plant. See in below path,

    SPRO > Production > Material requirements planning > Planning > Define storage location MRP per plant.

    In this set option 1 for storage locations which you want to exclude in MRP for the plant.

    Thanks,

    Kumar