Work order Costs are showing under miscellaneous cost

sp0123
Participant
0 Kudos

cost-2.jpgcost-3.jpgcost-4.jpgDear Experts

When I am creating an work order with Labour and Components, instead of showing under Maintenance Labour cost, Stock Material Cost and Non-Stock material cost, all the cost gets clubbed under a miscellaneous cost. How to rectify the issue.

Please see the screenshots for more details

Accepted Solutions (1)

Accepted Solutions (1)

prashantmeshram
Explorer
0 Kudos

Hello Shiv ,

Go to SPRO and do configuration setting in setting for display cost

SPRO path : PM & CS--> Maintenance and service processing --> Basic setting --> Setting for display cost --> Assign cost element to value categories.

Contact your FICO team and get correct cost element for all value categories ( Like internal material , labour cost , miscellaneous cost etc ) and assign.

Once you assign correct cost element for stock material and non-Stock material , It will show in your planned and actual cost.

Thanks ,

Prashant Meshram