Hi i am using immediate TO creation on replenishment type,so while confirming a TO for particular material the system checks whether the material needs replenishment from the material master and creates a replenishment TO straight away, is thr any way to make the TO created after an delay or time slot like aftr24 hrs.

THX

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jun 26, 2007 at 03:42 PM

    Hi Terry,

    You need to uncheck the "immediate TO creation" indicator for the particular WM movement type in the configuration and then schedule a background job to create a replenishment TO 24 once in 24hrs.

    Please expalin the situation why do you want the delay in replenishment TO creation?.So, that you will get a detail answers.Thanks.

    SAP TN.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.