we are implementing ECC 6.0 and SCM 5.0 APO/PPDS for UK/I client.

client wants to change the source of supply every month, client has 10 plants within UK and Ireland and Manufactured product is procured from the different plants.

Also,can we create the full vehicle load with the help of SNP?if yes, then how??

Thanks,

Regards,

Jignesh.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

you can do it by transportation lanes maintainance

Switch the block indicator on the maintainance for your products before the plannning run. Also you can think of lane validity or switching priority

Former Member
0 Kudos

Did you already considered an option with Quota arrangement with startdate and end date ?

/Shibu

Thanks for rewarding points if this is helpful