Hello Friends,

Can Any body lighten me regarding below issue...

We are budgeting for project in CJ30 T-Code. System also check the availability of Budget against actual postings on respective WBS Elements. But now My Question is what is the purpose of T.Code <b>CJ32</b>-Release Budget and when we will use this transaction.

When we put budget in CJ30.. it means we are releasing budget for the corresponding WBS Element. so what is the necessity of <b>CJ32??</b>

Thanks in Advance...

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 26, 2007 at 07:03 AM

    Hi Hari,

    Budget Release & Budget allocateion functionality in SAP is inline with business requirments. In most of scenarios, budget alloted, is n't the same as budget release as management of the company always try to optimise use of funds. One more benefit is through funds management complet budget control will happen say activity level budgeting can happen.

    Hope this will guide you to some extent.

    Regards,

    Biplab

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 26, 2007 at 03:56 AM

    Hi Hari Krishna

    Besides technical reasons, Budget release has got its own importance interms of administrative point of view also.

    Please also have a look at Budget updates (suppliments, returns, transfers etc) which follows the buget release functionalities in real time scenario.

    Enjoy SAP.....

    Regards,

    Sudhakar

    Message was edited by:

    Sudhakar Pappu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 24, 2007 at 06:39 AM

    Hi Hari,

    This transaction is optional. The following points will explain the requirement in a better way:

    1. Once you assign Budget in CJ30, it becomes your defined approved funds( and not the released Budget for that object).

    2. To ensure that the available Budget is not exhausted at an early stage; you release the Budget in Stages.

    3. Budget release means that you release parts of your current Budget so that that can be used.

    4. The release of the budget is optional. But its definitely recommended, since you will have a control on your spending.

    5.Very Important point: If you work with released Budget, You will have to carryout the availability check against the released Budget and not against the Current Budget. These setting you do while configuring the Budget Profile.

    Hope this helps.

    Warm regards,

    Srinivas Potluri

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 26, 2007 at 06:17 AM

    Hari,

    Using released budget, you can also benefit of using authorization restrictions. For example, you can have a team to allocate budget to your projects but just the project manager will be responsible for releasing it.

    So further control can be implemented in this direction too.

    Hope this helps.

    Thanks

    Martina

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.