Dear guys,

What is meant by validating MRP results ?

How it should be done

Pl reply

guru

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184627
Active Contributor
0 Kudos

Hi,

You can check the MRP results in MD04 transaction.

Here you can check the stock & requirement details such as requirement date,Purchase requisition/Planned order dates/sale order details & stock situation.

You can also check the dependent requirements & check for error messages (if any).

Regards,

SDS

Former Member
0 Kudos

Hi,

Planning Run:

Run MRP thru tcode MD02 Single item Multi level Planning

During Planning Run reqmts for a material are analysed and proc elements are

created.

Evaluations:

All the receipts and issue elements will be displayed

MD04 Stock / reqmts List

Md05 MRP list

MD06 collective access to MRP list

MD07 Collective acccess to Stock/ reqmts list

After MRP Run if there is any critical situation this will be displayed in the form of exception messages.

Ex message 96 stock has fallen below the safety stock

message 10 Bring the process the forward.

message 15 Postpone the process.

message 20 cancel the process

Based on the results Mrp controller works whether Production need to be carried out at a particular date or need to postpone the production.

Regards,

nandha