Hi,
When I create a simulation version for a cProjects "Program" (see Multi-Project Management in the online library), the assigned projects and phases are not included in the simulation. Per documentation in the online library:
"If you create simulations or snapshots for a project that is linked to another project (program, master project for a subproject, or a project with a mirrored task), the system copies the link and shows the linked operational object. If, for example, you create a simulation of a program, the simulation is also given the operational projects that belong to the program. In the same way, the simulation of a master project is assigned the link to the operational subproject."
Could you please tell me what am I missing?
Thanks in advance,
Guillermo
Hi Guillermo,
I just followed up with a colleague. Simulation is only possible for single projects but not in a multi-project setup.
Regards
Dirk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Guillermo,
please ellaborate on your specific question / requirement and I will be happy to follow up.
Thanks
Dirk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.