Upgrade to sap system s/4 - estimate the time required to do custom code checks

Hello,

I need to estimate the time required to do custom code checks and fix problems.

My feeling is about the range time between:

3 Months - 1 Year .

Is it a good range time to do this activity ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jul 14, 2017 at 05:27 AM

    Hello Eliram,

    I would suggest that your run a SAP Readiness Check for SAP S/4HANA. That includes a custom code analysis that should give you a good indication of what you are looking at and therefore how long the remediation might take:

    I also wrote a blog how to Make the SAP Readiness Check for SAP S/4HANA work for you:

    Best regards

    Frank

    Add comment
    10|10000 characters needed characters exceeded

    • You'll see numbers and types of problems .

      Let's say if you will get:

      1,000
      or 10,000
      or 100,000
      objects development with problems

      How do you estimate the required time to do custom code checks there's any formula ?