on 06-22-2007 6:31 AM
Hi all,
We are facing a serious problem with subcontracting PO,
Scenario - A subcontracting PO is placed & the items are issued to the subcontractor. Most of the times the materials in the BOM gets updated after the items are issued (due to design modif's) & this is where the problem begins. At present we are facing big problems in updating the BOM in sub-con PO as it needs to be updated item by item.
- Would like to know is there anyway, i can update the sub-con PO with the new BOM all at once, instead of item by item.
- Also what movement is required to receive back to store, those materials which are no longer required in the new BOM
- Can i issue new materials to the sub-contractor referencing the same sub-con PO?
Would highly appreciate if someone could give the SAP flow for handling this issue ASAP.
Vivek
Dear,
You can move back the Stock by 542 Mvt.
For BOM updation Click on PO Explode BOM.
Regards
Biswajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just got this info from SAP library-
Reading a New BOM
If one of the following questions is answered with yes then a new BOM cannot be read in:
Do purchase orders already exist for non-stock components or components with direct procurement?
Have components already been taken from stock?
Are there transport requirements?
Are there future change records from the confirmation (parallelization)?
Are there goods movements containing errors that have not been processed?
Based from the above, since the components have already been taken from stock & issue to sub-contractor, we wont be able to explode BOM from PO right?