Skip to Content

Purchase requisition from PM order is not reduced in FM

Jul 13, 2017 at 12:25 PM


avatar image

Hello there

I use external activity in PM order with reference to framework purchase order, to create PR and then SES (with reference to the PR) . The framework order dose not consume budget (Account assignment category 'U'). The SES and the PR consume budget. This is SAP best practice for logistic scenario "Accelerate service Purchase"

The problem is that the SES dose not reduce the PR in FM. As a result the budget is consumed twice.

Has anyone encountered such a problem?

thank you

Uri noyman

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers