DP95_Resource related billing

Dear all,

Can we ensure that the closed projects' info does not reflect while executing Tcode DP95. Projects which are closed in 2001-2002 are also refelcting in this report.

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jul 03, 2007 at 07:06 AM

    Resolved

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Sudhakar,

      logically, Closed projects should not get executed for DP95.

      It was an ABAP error. Actually system is executing open projects while executing DP95 but only was displaying error of closed projects. When I sat with the user and understood the problem, user is giving range for the projects, some of them are closed, so system is giving error for the closed projects. open projects are only executed but system is giving error message for the closed projects which is not required. So found out that there is an error in Abap which our programmer has corrected.

      The problem was user was unable to explain on mail/phone. when I personally sat with her, found out the problem.

      Thanks