Budget Issue in PS-PP integration process with ETO (Engineering to Order) scenario:
When manufactured Semi Finished Good Block 01 is moved from WBS BK-01 to WBS GA-01 for further manufacturing process at GA-01, we get error message of budget exceeded.
We have checked the scenario using WBS grouping at Project level but all procurement & production order happens at project level & we do not get budget control at each block level WBS as required by business.
Please suggest