we design process steps in IR to implement BPM. Are there anything that we do in congiguration to implement BPM ?? I believe there is noting to do in configuration. Any comments on this particular issue ??

thanks

kumar

Accepted Solutions (1)

Accepted Solutions (1)

justin_santhanam
Active Contributor
0 Kudos

Kumar,

There is no config needed, but you have to import into ID as you know.

Also one more thing, after importing to ID. If you make any changes to BPM in IR. Then come to ID and double click on the imported BPM, click edit ,there u can find an option of refresh interfaces,select that. Now activate again.

Thats it!!

Best regards,

raj.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi palnati,

u have to import the integration process form IR and later on if u need change something in IR u can just refresh the integration process in ID.

And one more thing...if u have multiple reciever ,u can provide the condition(xpath/context object) in the reciver determination.rest all r same as we do in non BPM scenarios....activate all your object and ur scenario is ready for test!!!

Regards

Biplab