on 07-11-2017 3:31 PM
HI Gurus,
My Client has the below requirement for which i am not able to find a standard solution,
1. Initially MMRV Should start which will allow posting for previous year, just before the schedule job runs for mmpv to close the period,
2.Once the closing period job (MMPV) is complete.the system should run another MRRV job for Disallow back posting generally.
Please advise how i can address the issue.
Thanks in advance
Hi,
let me know if you are running Batch jobs
what is the timing difference between MMPV and MMRV
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.