Basic finish date of individual WBS is showing Project End Date

Hello All,

In a project I have multiple WBS with multiple networks & internal activities interlinked.When I a scheduling the project (from the Project Definition level), the WBS Basic dates take the Earliest Start Date & Latest Finish Date (which is the project end date). Is there any way to get the Basic finish date as Earliest Finish Date?