Help with planning strategy

Jul 10, 2017 at 04:28 PM

19

avatar image

I have a marketing forecast (PIRs/LSF) I load quarterly for the next 3 months.

We have a custom PP system, and I'd like to enter a short term 5-day production schedule into DM. This will be a custom interface. I'm thinking of using customer requirements (KSL) to reflect the daily demand but am open to other suggestions.

So for the 5 days where LSF and KSL overlap, I want MRP to only plan against the KSL elements. I don't want KSL to consume the LSF, since the KSL production demand is the absolute accurate demand. After the future 5 days, MRP can continue to plan against the LSFs.

Does SAP have a planning strategy for this? I should add that all MRP planning is against raw materials.

Thanks, Vlad