Skip to Content
avatar image
Former Member

Create iPPE data in APO

Hi everybody,

We have ECC 6.0 system and implementing APO 5.0. We realized that Model Mix Planning meets the production planning requirements. However, we do not have DI system (which uses iPPE data).

Is it possible to create iPPE data directly in APO manually without transferring from DIMP system, and then planning using MMP in APO, and transferring these planned orders to R/3. I read the note below in help.sap.com. According to this note, it is possible to create iPPE in APO. Then can we say that we can use iPPE data with standard R/3 system (i.e. not a DIMP system)?

-


Prerequisites for "Generating Production Data Structures (PDS) from iPPE Data ":

1)You have transferred the iPPE data from the DIMP system via the Core Interface in SAP APO, <i><b>or created iPPE master data in SAP APO</b></i> and maintained production versions.

2)You have checked the data in the DIMP system with the iPPE consistency check.

-


Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jun 21, 2007 at 12:06 PM

    Any comment please?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      I am not sure , waht master data requied in ECC for Planned order transfer from SCM , but you can cerate ippe struture in SCM for Planning run.

      Lav Mishra