on 07-11-2017 7:08 PM
Hi gurus,
If we have say 10 operations , and if 3rd , 7th, 10th operations are milestone confirmations..what if we do mile stone confirmation for 10th operation? will all the operations gets confirmed? Please answer
Hello Shruthi
Before opening a thread, I suggest you to always make some research for yourself and also to test the scenario in your internal test system.
If you read carefully the information about milestone confirmation provided in SAP Help, you will find the answer to your question:
https://help.sap.com/saphelp_erp60_sp/helpdata/en/2b/04b753128eb44ce10000000a174cb4/frameset.htm
After that, you can set up an example on your internal system and check by yourself.
Best regards,
Caetano Almeida
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Shruthi
Before opening a thread, I suggest you to always make some research for yourself and also to test the scenario in your internal test system.
If you read carefully the information about milestone confirmation provided in SAP Help, you will find the answer to your question:
https://help.sap.com/saphelp_erp60_sp/helpdata/en/2b/04b753128eb44ce10000000a174cb4/frameset.htm
After that, you can set up an example on your internal system and check by yourself.
Best regards,
Caetano Almeida
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.