required to assign multiple person in single service order (PMCS)

Jul 12, 2017 at 08:30 AM

54

avatar image
Former Member

Dear Experts,

I would like to forward my question for your kind support that i want to assign multiple person for single activity in service order (PM CS)

sap
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Nic Teunckens Jul 12, 2017 at 12:48 PM
0

Please revise SAP Help on this. You can allocate Multiple resources (Personnel) via Split-Tab on the OrderOperation : link

The Operation must have Working-time allocated (a Number of Hours / Minutes). In that case, the Split-Tab will be shown. Resources (Personnel Numbers) can be entered ...

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Jul 16, 2017 at 07:53 AM
0

thanks, as your advise i have mentioned the time but the split-tab is not show, would you guide me step by step please.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hello

Could you check if your Operations have a Working Durations of "X" Hours or "X" Minutes assigned?

(I do not have access to a SAP System now, but see below Links on a Work Duration filled out)

Link OrderHeader - see Data under First Operation

Link OrderOperation - see Operation Work / Duration filled

Upon adding Working-Hours/Days/Minutes, the Split-tab should be shown as the Requirement-Assignment-Tab ...