Hi,

I am working on PR Workflow. There is a scenario in which the approver uses a release code to reject the PR release instead of rejection icon. So it means that the approver will recieve a work item, on execution will goto ME54N where he will have two options one with release code A1 and other with R1. If he releases the one with A1 then it is released.If he releases the R1 then it is rejected.

My problem when the approver rejects the PR using release code R1 the workitem still remains in his inbox.I want to complete this work item and follow the Rejection path.Kindly suggest how to handle this

The Release Statuses in SPRO are maintained like this

A1 A2 R1 Release indicator

X X Blocked

X X R Rejected

X X 2 RFQ/purchase order

X X X 2 RFQ/purchase order

Kindly suggest how to handle this

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on Jun 13, 2007 at 08:20 AM

    Are you sure it is the same work item that is still in the inbox? Sounds very strange as task TS00007986 has 4 terminating events defined (assuming you use workflow template WS00000038). But then again, you haven't said if you are creating your own workflow or not, so that's just a wild guess on my part.

    Add a comment
    10|10000 characters needed characters exceeded

    • As Prabhakar pointed out, you are not rejecting, you are releasing. That is why I don't understand why there is no event created. The ordinary "Released" event should occur. Have you verified using the event log (transaction SWEL, with SWELS first to turn logging on if necessary) that no events are created when you select release code R1?

  • Posted on Jun 13, 2007 at 10:00 AM

    Hi,

    These is no seperate Release code for Rejection.

    Please Just check and test it again.

    We have seperate Button left side for Rejection in that ME54N.

    Thanks and Regards,

    Prabhakar Dharmala

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 13, 2007 at 10:01 AM

    So in your case Requistion is never rejected, if one selects R1 release code and release it , that means it s rejected if A1 or A2 that means it is approved.

    Guess standard worklow will not work in this case.

    Thanks,

    Shweta

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.