Skip to Content
0
Former Member
Jun 13, 2007 at 07:26 AM

Alternate parts considertion in MRP

28 Views

Is there any facility to specify alternate parts for a part in BOM?

If we can do that, can MRP be aware of alternate part quantity available before suggest PR? for example, if part A is an alternate part of part B, then even if Part A is in shortage but Part B quantity is available, MRP should suggest using Part B instead of firing additional order for Part A.