Dear All,

I have project scenario where material requirments should come from Projects for purchase & production process separatetly. I tested with below project structure, but there is duplication of material requirments happening.

In this conenction, there is two WBSElements say Purchase & Inhouse manufacturing under WBSE Manufacturing Process. ROH items are assinged to Purchase WBSE & HALB items to Inhouse manufacturing WBSE. FERT material (Which is material BOM) is assinged to manufacturing WBSE. Aftre MRP run, there is duplication of requirments for ROH and HALB items, as ROH & HALB items are inside FERT item BOM.

I would like to request all, to suuegst in preventing duplication of material requirements.

Thank you in advance.

Regards,

Biplab