on 06-07-2007 6:24 PM
Hello,
I am trying to create a subcontracting PO. First, I enter the material I want to order and the item category for subcontracting (L) in the order item; then I press Enter. However, the screen for component processing is NOT displayed. For this reason, I selected "Material data" and clicked on the "Components" button and BOM is displayed. But, there are two BOM versions for this material and only get one of them (the wrong one). How can I get the right one?
Regards,
Carlos Piana
Functional Leader MM
La Universal
Guayaquil, Ecuador
Go to Item -> Component -> New BOM explosion. BOM will be redetermined.