Hi SAP Experts,
I have a question about MRP.
Can we work MRP with subcontractor stock?
Let me explain, the MRP could not to generate new planning orders if I have subcontractor stock. For example:
In MD04 transaction
MtlRes 100- units
MtlRes 100- units
MtlRes 100- units
SubcSt 300 units
If I have this situation, the MRP run could not to generate planning orders because the subcontractor stock recover the quantity.
This problem (almost) drive me crazy. I really appreciate any help.
Thanks in advance.
Dear Demetrio
Please note that the logic for subcontracting was changed as of release
4.0A.
As of release 4.0 the net requirements calculation for components to be
provided in subcontracting takes into account that the provision stock
can only be used to cover the corresponding requirement of material
provided. The provision stock that is already available from a
subcontractor (vendor) can only therefore be used to cover the
requirements of material provided at this subcontractor.
The system uses only the stock that has not been assigned to a
subcontractor as unrestricted-use stock to cover all requirements.
For further information about this issue please consider the below QA. With the modification of note 170597 the old logic can be achieved. Please notice that it is a modification note.
1. Question
Why does the MD04/MD05 display an own segment for subcontracting as of Release 4.0B and how does the materials planning work with this new logic?
Answer
The logic regarding the subcontracting was changed as of 4.0. This is explained in detail in the release notes for 4.0A:Planning of the components to be provided for subcontracting
Material Requirements Planning -> Planning Execution -> Material Requirements Planning: Planning of the components to be provided for subcontracting
2. Question
Why does the third-party order processing for subcontracting work differently as of Release 4.0B?
Answer
The (Pseudo) Third-Party Order Processing for parts provided together with the own segment for subcontracting results in problems and can result in inconsistencies. This is described in detail in Note 214298.
As of Release 4.5A you can implement the third-party order processing with subcontracting MRP areas (refer to the corresponding documentation).In addition you can use a modification to reset the system to the behavior before 4.0A, refer to Note 388479. As of Release 4.7, BAdI 'MD_SUBCONT_LOGIC' allows this without a modification.
3. Question
Why does the discontinued part for subcontracting not work?
Answer
You cannot divert requirements of material provided to the follow-up material. The reasons are described in detail in Note 43636, section 6.
4. Question
Why does the system not display the requirements of material provided in the storage location MRP area, as expected?
Answer
Requirements of material provided (subcontracting requirements, material staging requirements) never reach a storage location MRP area, because later you cannot post the withdrawal from this MRP area.
The withdrawal of the components (to be provided) during the goods receipt for an SC procurement proposal occurs always from the stock with subcontractor, which is managed - from the viewpoint of the inventory management - on plant level and has no storage location reference.Refer to Note 503497 for details.
5. Question
Why does a requirement move from the subcontractor segment into the plant segment and is covered there although it appears already to be covered in the subcontractor operation segment by a receipt element (Pseudo third-party order processing for the subcontractor)?
Answer
The corresponding receipt element must standardly always be within the rescheduling horizon. This is required (due to technical reasons) even then when the input itself does not have to be rescheduled, so that the net invoice can deliver consistent results for the subcontractor segment together with the rescheduling check.
If the receipt element occurs after the requirements date, the corresponding element must participate in the rescheduling check (Transaction OMDW).
Regards
Soundar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You would have maintained the subcontractor as a storage location.
In storage location customising or in MRP4 you can exclude the storage location stock from MRP. So during MRP subcontractors stock will not be considered
IF helpful reward your points
Regards
Ranga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1.Try the options given in BOM as material provided by vendor/ matlr provided by customer.
2.In the availablity check options in the spro img, check the indicator w/o subcontractor stock.
T.code opjk/opjj
Regards,
SDS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
mrp areas enable u to plan materials,which are required in different production areas,storage locations or subcontractor separetely from each other.to activate mrp for mrp areas(img-- activate mrp for mrp areas) tcode --OM0F.
create mrp areas(define mrp areas)
create mrp area segment in material master(mrp1 view)
in your case check your settings for subcontracor area.
award points if useful.
Regards,
N.Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.