Requiremnet type

Hi,

Is there any relation between Requiement Type and Availability check?

Please explain me.

Mnsr.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on May 31, 2007 at 10:40 AM

    Mnsr,

    No direct relationship, but requirement class is assigned to requirement type. Requirement class defines the availability check.

    Hope this helps...

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 31, 2007 at 10:43 AM

    Hi,

    No

    Following is link bet remts type and reqmt class and strategy and material

    To make up a product we need some requirements in the form of demand.

    This requirements are independent requirements and customer requirements

    To create a demand Program the Demand Management uses PIRS and

    Customer Requirements and we need to define a planning strategy

    Planning strategy define the methods of production for planning and

    manufacturing a product.Using these strategies we decide whether

    production is triggered by sales orders or not ie MTS OR MTO

    Requirements classes:

    We need to define requirements class which contains control parameters

    for planning and consuming the PIR and customer requirements.

    This Requirements class is to be assigned to requirements type

    By doing this we are indirectly assigning the control parameters to

    strategy via Requirements type

    This Requirements Type is to be assigned to strategy

    Strategy should be assigned to strategy group

    Strategy group is to be assigned to Material in Mrp 3 view or via MRP Group

    Regards,

    nandha

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 31, 2007 at 10:45 AM

    The availability check is controlled by means of the same elements as the transfer of requirements:

    Requirements class

    <b>Requirements type</b>

    Checking group

    Checking rule

    Schedule line category

    Strategy group

    Planning strategy

    Please refer to the below help link which will give you a clear idea on avaialbility check and requirement types -

    http://help.sap.com/saphelp_46c/helpdata/en/fc/836ae8f66111d2b6a70000e8359890/frameset.htm

    http://help.sap.com/saphelp_46c/helpdata/en/6f/fdeb47b535d1118b3f0060b03ca329/frameset.htm

    Hope this helps you.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.