When I create a SO of project requirement, the line of "ProjSt" will appear in MD04.

If this item of SO is cancelled, the "ProjSt" line will disappear.

But after delivery and post goods issue,the "ProjSt" line will not disappear.

Could you tell me when will the line of "ProjSt" disappear?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jul 18, 2017 at 11:06 PM

    you probably still have independent requirements as shown in OSS note 2084268 - How to assign a planned independent requirement to a WBS or a sales order

    Can you post a screenshot from your MD04

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 01, 2017 at 07:56 PM

    The Project Stock identifier should disappear when there is no more inventory, requirements, or supply objects for that WBS. Is there any stock?