When will the line of "ProjSt" disappear?

Jul 06, 2017 at 01:43 AM

50

avatar image
Former Member

When I create a SO of project requirement, the line of "ProjSt" will appear in MD04.

If this item of SO is cancelled, the "ProjSt" line will disappear.

But after delivery and post goods issue,the "ProjSt" line will not disappear.

Could you tell me when will the line of "ProjSt" disappear?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jürgen L
Jul 18, 2017 at 11:06 PM
0

you probably still have independent requirements as shown in OSS note 2084268 - How to assign a planned independent requirement to a WBS or a sales order

Can you post a screenshot from your MD04

Share
10 |10000 characters needed characters left characters exceeded
Ken Melching
Aug 01, 2017 at 07:56 PM
0

The Project Stock identifier should disappear when there is no more inventory, requirements, or supply objects for that WBS. Is there any stock?

Share