cProjects 4.0 - Evaluation - Threshold

In cProjects 4.0, under Evaluation > Define Threshold Values, when I click on the a/b Form field element, I am not able to define a formula which involves the status of the project element.

For e.g. I want to set a threshold value for a Project Element (Task) which is 5 days from completion and which has a status 'Released.' I do not see the element SYSTEM_STATUS which will help me use this in the formula.

What's the way out?

Thanks all very much.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on May 30, 2007 at 07:02 AM

    Hi Bittu,

    You first need to setup a layout with the necessary attributes in "Define extract layout". Than you need to select this layout in the column "Eval- Layout" in the treshold value definition. Afterwards you can use those fields in your formula, like

    "System Status for an Object as a String = 'Released' AND ( Current Date + 5 ) < Calculated Finish Date"

    Best regards,

    Daniel

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.