Project availability control tolerance limits

Jul 07, 2017 at 12:01 AM

25

avatar image
Former Member

Hi All,

Currently, final user is asking us to update the Project availability control tolerance limits, then, they need to increase it for 5% of budget, because off currency exchange rates with the local currency and foreing currency.

We already did some test cases with only one budget / planning profile, we created WBS and generated the Purchasing Requisition from Networks and Purchase Orders and the new customizing is working very well.

Our question is regarding with all the Budget which are in usage with the all the WBS that were created before the new customizing. What will be the possible consequenses and the follow steps for the new configuration for the availability control tolerance limits of WBS which were created before the customizing?

Thanks in advance.

Regards.