Hi all,

I’m working with cProjects 3.1, <b>not installed in CRM Platform</b>. At this moment I have accounting integration, the system create an internal order to collect the costs.

My doubt is:

If I want to install the cProjects 3.1 in the CRM platform, I’m going to have the PS integration (costs and revenues are collected on the Project WBS), but I’m going to lose the accounting integration (internal order) or not?

It’s possible the multi-object integration (Project and Internal order)?