Hi Gurus,
While creating Production Order, am getting an error message as " <b>no control record for Activity Type"</b>.
Please advice this is urgent..
Thanx in Advance.
Hi pradeep
1. check the workcenter costing view for the costcenter and the activity types.
2. for the same cost center and the corresponding activity types check in KP26 for price planning.
3. if all ok try CK11N std cost estimate if you get the costing results then everything is fine now your issue is solved
Hope this helps
SK
REWARD YOUR POINTS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pradeep,
This is because the cost centers in work center are not linked with activity type.
The cost center and activity type has to be maintained in KP26 transaction
this is generally maintained by FI people
If helpful reward your points
Regards
Ranga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pradeep
Check whether you have assigned the activity type for the work center you are using
You can assign the activity type for the work center in CR02 under costing tab
also assign the cost center
Then Go to KP26 tcode, there you have to assign the activity type to the cost center
Hope this helps, If so pls rewrd points
regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.