Im working with a configurable material, Im using 25 planning strategy for my configurable product and 70 planning strategy for the possible components for the product, after I create the sales order, I run MRP to get the planned orders for the product and components then I convert the planned orders, as a result, a production order is created to get de finished product for that sales order, Im agree with this but for components, system askme to have a stock (if I dont have it, system ask me to purchase it) for that sales order and client in specific and what I want is to have the components in a common stock and take them for the production order created for the sales order in specific.
Do I need to use other planning strategy?, I also tried with 89 (FG) 70 (Components) planning strategy and I have the same problem.