cancel
Showing results for 
Search instead for 
Did you mean: 

In WBS Assigned value showing in controlling area currency

Former Member
0 Kudos

Hi,

We have controlling area currency as INR & Company code currency as LKR.

I have created budget profile as below.

1. Activation type as 1
2.Overall, Release & Object currency check box selected in Availability control field.3.Object currency & Default object currency selected in Budget field

& Tolerance limit is maintained as 80% warning & 100% error.

I have done budgeting to WBS as 35,000 LKR & PO was created for 35,000 LKR but when I checked CJ31, assigned value is showing as 14,000(it is showing in INR) & in S_ALR_87013558 it is showing as 35,000.

& because of this system still allow to create PO upto 21,000 LKR(35,000- 14,000).

Why system showing assigned value as 14,000?

Please help.

Accepted Solutions (0)

Answers (0)