Hi

I am facing an strange issue in ccBPM scenario.

My flow is WS sending the data to PI. From PI the data is to manipulated in MDM and the same should get updated in ECC. Then ACK should be triggered to WS from ECC.

So far the flow is working fine and no issue happens. Last week data base migration has been. After that this flow were struck in queue saying "Permanent error in BPE inbound processing". When i check the "Display Trace", it gives error in very first mapping step. But when I try the payload in mapping, there were no discrepancy found. This is to strange.

I have checked cache its fine. There were no workflow process available. There were no Exception was configured in BPM hence no PE available in Moni.

Kindly help me to fix this.

Regards

Amarnath M

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Raghuraman S Jul 06, 2017 at 09:28 AM
0

Do some dummy changes in mapping, Activate it and try.

Also ensure Data is correct and statisfying the BPM process flow.