report CNE5

Hello all.

I'm executing CNE5 and BCWS and BCWP values are not appearing.

"Aggregate planned percentage of completion", "Non-aggregated planned percentage of completion", "Aggregated actual POC",.... data indicate 100%.

Could you help me??.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jun 06, 2007 at 04:48 AM

    Hi,

    In CNE5 report, press F5 i.e. Choose fields....

    Select fields like BCWS,BCWP,Aggregate planned percentage of completion,Non-aggregated planned percentage of completion,Aggregated actual POC and import it into Selected fields option.

    Click ok and then see these fields appearing CNE5 report.

    Hope this helps.

    Regards

    Tushar

    PS: Reward points if answer is useful.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.