on 07-04-2017 6:09 PM
I have Semi finished F for making it .I can use E or D .E&D are semi finished.
I have used Alternative item bom E as 20% D as 80% When I Run Mrp for 10 number
I am getting only one planned order for 10 but i should get two different planned order
1 Planned order should consider E - with 2 numbers
2 Planned order should consider F- with 8 number
MRP generated 1 planned order for header material F and in components overview of this planned order, you should be able to see E with qty 2 and D with qty 8. And, when showing E in MD04, the dependent requirement should exist with qty 2; when showing D in MD04, the dependent requirement should exist with qty 8.