What are MRP settings for Demand Management?

Jul 04, 2017 at 11:11 AM

50

avatar image

Hi Experts,

We are following two ways for updating demand for material in SAP. One is through MC94 and other one is from MD61.

My question are,

1 - If we have monthly schedule with us and we are updating through MD61. What are possible settings for MRP run and MRP1, MRP2, MRP3 and MRP4 views.

2 - How we can delete old demand that are showing in MD04 at material level not plant level.

Please advice.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Amit Sharma Jul 05, 2017 at 07:13 AM
0

Hi,

1. MRP type, MRP controller, Lot size, Procurement type, schedule margin Key, Safety stock, selection method, Individual/collective requirement etc it depends upon business which ever field is required and you want to utilize that functionality.

2.You can delete manually in MD04 , Remove demand from MD62 ,

https://archive.sap.com/discussions/thread/2154141

Regards,

Amit

Show 2 Share
10 |10000 characters needed characters left characters exceeded

There were some error in posting date while deleting demand. It is done now. And yes I followed your ans#2 for this.

For first question I knkow these settings are required but I just want to know the best combinatio of MRP type and Lot Size?

PD with EX or PD with (MB/WB/TB)??

Thanks for your support.

0

It depends upon business which lot size they want to use.

EX- Lot for Lot

MB - Monthly --> In this requirement of whole month will be clubbed together

Same as other lot sizes.

Regards,

Amit