on 07-03-2017 8:01 AM
Hi All
I am setting up Embedded EWM on S/4HANA. Testing GR process with /SCWM/GR transaction. Product is batch managed.
Issue is that ECC material master plant/sloc1 view has SLED period indicator as 'M-Month'. Minimum shelf life as '1' & max as '24'.
But product master in /SAPAPO/MAT1 has both minimum & maximum period as '24'. System does not allow this to be corrected in /SAPAPO/MAT1 Or /SCWM/MAT1. Behavior is same when material has indicator 'D-days'.
This is incorrect. Could not find any configuration or note to correct this. Please do let me know if you have faced this issue. Waiting for your response. I am rising this to SAP in parallel. Thank you.
Regards
Phani