Material staging to PSA

Former Member
0 Kudos

Hi experts

How can I do this?

I have in the warehouse, two pallets of 25 units each. And I have a process order of 30 units of these materials... I want to transfer both pallets to PSA.. and then I consume 30 units (1 pallet and some of the other) and the rest of the pallets I'll transfer them to the warehouse.

I try to do with staging indicator (1,3 and 5) and always I have the same problem:
sap.png

Accepted Solutions (1)

Accepted Solutions (1)

Ajit_Routray
Active Contributor
0 Kudos

Hi Francisco,

It looks the replenish quantity is more than WH Request ( Posting change Quantity ).

Can you please check the replenish quantity in Tcode-/SCWM/PSASTAGE - Assign Bin to PSA/Product/Entitled in Warehouse Number?

I guess you maintained a value ?

If yes , Please change to 1.

Qty Calc. Type-> Calculation based.

Please let us know if issue still persists.

Kind Regards,

Ajit

Former Member
0 Kudos

Hi Ajit,

These are my steeps.psa.png

Ajit_Routray
Active Contributor
0 Kudos

Hi Francisco.

Thanks for screen shot.I tested one of my requirement as per the attached screen shot and works in PMR.Please maintain the unit in PSA and let us know the results..

Kind Regards,

Ajit

psa.png

Former Member
0 Kudos

Hi Ajit...

The same problem...

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Francisco

I have done production staging from /SCWM/STAGE transaction for PMRs using indicator 3- Single order staging. I used rounding rule in process type to control picking quantity. Have you explored this? Check it out.

Regards

Phani

pic1.jpg

Former Member
0 Kudos

Hi M.N. Phani Sai

When I execute these transaction, SAP says that there aren't quantities to staging.error.png

Former Member
0 Kudos

I have worked with PMR... And SAP does not allow create WT...

It's SAP S4HANA.

Best regards

pmr.png

Former Member
0 Kudos

ajit.routray.ewm