SAP PM ModuleTask List transport

Jul 16, 2017 at 05:37 PM

50

avatar image

Hi guys, can someone tell me how to transport a completed maintenance task list/ maintenance plan from quality server to production server?

If this is not possible , is there any way to download the task list to my hard disk and then upload it again?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Jul 17, 2017 at 09:22 AM
0

Hi James,

Is there any particular requirement to transport Task List ?

Task List is a Master data, you can use LSMW to create the data in Production Server. Maintaining the complete data in Excel sheet and it can used for upload.

Regards

Terence

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks Maria Terence for replying. I was out of this forum for quite a while, sorry for the delay in responding. I will check and get back to you.

0