Effectivity in ECR/ECO

Can some one help me to resolve my query?

We are having ECR system developed for existing system and we have not utilized all the provided features of SAP 4.6C

Now we are going for SAP ECC6.0 where-in we ant to use effectivity parameter for controlling the change process

Can somebody tell me something more on effectivity type like what are famous effectivity parameters and how they can help a business in controlling change process.... n where all it effect after change will take place...?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on May 21, 2007 at 04:32 AM

    Hi Kamal,

    When you process an object (such as a BOM item) using a particular change number for the first

    time, the system generates a new processing status (change status).If your organization does not use parameter effectivity, these changes simply have time-related validity, which means that a change status's validity extends from its valid-from date to immediately before the validfrom date of the change status following.

    However, if you do use parameter effectivity, you can also make a change status's validity dependent on other criteria, such as serial number or customer.

    <b>For more details provide your email Id, so that i can send you the detailed document on working with Effectivity paramaters</b>.

    Regards

    Rehman

    <b>Reward Your Points</b>

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi heijo

      I may not be able to give fully satisfactory answer but this may help you in solving the problem

      SAP gives two parameter effectivity one as DATE and other as SERIAL NO

      apart from choosing parameter effectivity for change on material, you have link these changes with release key then assign them priorties and rank

      after which system check the changes on material in following manner and decide the valid change

      1) change with release key

      2) change with higher priority

      3) change with higher rank

      after this process system assign change to material

      When you are doing change wrt SERNO then system checks only release key and then change with higher rank gets implemented

      according your other processes get effected

      Rgds

      KAMAL

  • author's profile photo Former Member
    Former Member
    Posted on May 30, 2007 at 07:06 AM

    Hi,

    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/LOECH/LOECH_EFF.pdf>

    Kamal, if your previous issue is solved then you can close this thread with your reward points for your helpful answers.

    and can open the new thread for any more queries.

    Rgd

    Rehman

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.