Hi all,

Good day,

Unit Test, String Test, Integration Test, Production Cutover Test, User Acceptance Test, Performance Test, Data Conversion Test, etc are different types of Tests

1. Can we do all these tests using eCATT?

2. Usually what kind of testing is required for SAP 4.X to ECC 6.0. upgrade project

Regards,

KC

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 16, 2007 at 12:13 PM

    Hi Kalyan,

    You can perform the kinds of tests you have mentioned with eCATT very well.

    In Upgrade project, you will have some defined landscape say development, quality & production. All servers in synchronization with each other.

    So first you will do the upgrade strategy on dev box. After everything is done as part of upgrade on development, you will verify all the business scenarios who have undergone changes and the related linked scenarios in development server. Also same test will be carried out in quality server, which has not yet gone for upgrade.

    Both the tests should match in terms of expected output. If the output match, then only you go ahead and transport all the changes to quality server from development server.

    Hope this sort out your query.

    PS If the answer solves your query, plz close the thread by rewarding each reply.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Kalyan,

      1. eCATT is very much integrated in WAS 6.20 server. Also it is available with SAP Solution Manager. So recommended is to use the tool from Solman and do the recording on Quality server. At final testing time, pass different data to these recorded scripts in solman & execute on quality.

      If you don't have solman server, then have eCATT recording done on quality itself. eCATT is <i><b>NOT RECOMMENDED</b></i> for <i><b>Productive environment</b></i>.

      2. The recording can be done by either the consultant or the client depending on the kind of business that is happening between the two. Ideally, consultant will do the recoding but the test case will be given by client.

      3. eCATT is totally integrated into test workbench. Find the following link of my weblog talking about the test workbench in eCATT -

      eCATT Scripts Management Via Test Workbench(Part V)

      /people/sapna.modi/blog/2006/04/13/ecatt-scripts-management-via-test-workbench-part-v

      Find my series of weblogs for more details.

      Hope this solves your query.

      PS If the answer solves your query, plz mark the query as<i><b> Solved</b></i> by closing the thread.